Drinking water and domestic wastewater infrastructure work in the western sector
Federal contribution
$2.6M
$2,637,000
Federal share49%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Sainte-Marie
- Construction start
- Jul 12, 2017(actual)
- Construction end
- Feb 2, 2018(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2017
- Construction end14 months earlyforecast Mar 31, 2019
Also in Sainte-Marie