Drinking water upgrade

Cap-Saint-Ignace, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.1M
$1,059,801
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2017201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 16, 2017(actual)
Construction end
Feb 10, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast May 8, 2017
  • Construction end6 weeks lateforecast Dec 31, 2019