Drinking water upgrade
Federal contribution
$1.1M
$1,059,801
Federal share50%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2017201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Cap-Saint-Ignace
- Construction start
- Oct 16, 2017(actual)
- Construction end
- Feb 10, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast May 8, 2017
- Construction end6 weeks lateforecast Dec 31, 2019