Raw Water Supply Upgrades

Michel Village, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$400,000
Federal share50%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Mar 19, 2018(actual)
Construction end
Nov 22, 2018(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48913 in the federal list. How to read these figures.