Treatment of wastewater, water filtration plant of drinking water and patches to the network
Federal contribution
$242,157
Federal share50%
of $484.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 3, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Deux-Montagnes
- Construction start
- Sep 29, 2017(actual)
- Construction end
- Jan 31, 2018(actual)
Against the original forecast
- Construction start13 months lateforecast Sep 13, 2016
- Construction end8 weeks earlyforecast Mar 31, 2018
Also in Deux-Montagnes