Sanitary sewer extension, Highway 397 North and South and 1st Street West areas
Federal contribution
$724,500
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 6, 2017
20172018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Barraute
- Construction start
- Jun 27, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Nov 7, 2016
- Construction end2 weeks lateforecast Mar 15, 2018
Also in Barraute