Sanitary sewer extension, Highway 397 North and South and 1st Street West areas

Barraute, Quebec

completeWastewaterCWWF
Federal contribution
$724,500
Federal share40%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 6, 2017
20172018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Barraute
Construction start
Jun 27, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 7, 2016
  • Construction end2 weeks lateforecast Mar 15, 2018