Replacement of the drinking water storage reservoir
Federal contribution
$816,305
Federal share50%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 3, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Saint-Épiphane
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Jan 19, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 16, 2017
- Construction end14 months earlyforecast Mar 31, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48954 in the federal list. How to read these figures.