Cloverdale Athletic Park Multi-Sport Facility and Fieldhouse
Federal contribution
$1.9M
$1,919,463
Federal share33%
of $5.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
201820192020
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Surrey
- Construction start
- Jul 10, 2017(actual)
- Construction end
- Apr 17, 2020(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 23, 2017
- Construction end2 months earlyforecast Jun 30, 2020
Also in Surrey
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48972 in the federal list. How to read these figures.