Water Systems Upgrades
Federal contribution
$577,357
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20172018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Sainte-Marguerite
- Construction start
- Jun 26, 2017(actual)
- Construction end
- Nov 6, 2018(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2017
- Construction end5 months earlyforecast Mar 31, 2019
Also in Sainte-Marguerite
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48977 in the federal list. How to read these figures.