Water Systems Upgrades

Sainte-Marguerite, Quebec

completeDrinking WaterCWWF
Federal contribution
$577,357
Federal share50%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20172018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Sainte-Marguerite
Construction start
Jun 26, 2017(actual)
Construction end
Nov 6, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2019