Water System Upgrades

Massueville, Quebec

completeDrinking WaterCWWF
Federal contribution
$231,705
Federal share36%

of $635.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2017
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Massueville
Construction start
Aug 1, 2017(actual)
Construction end
Nov 1, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2017
  • Construction end5 months earlyforecast Mar 31, 2019

Also in Massueville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49039 in the federal list. How to read these figures.