Water System Upgrades
Federal contribution
$231,705
Federal share36%
of $635.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 24, 2017
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Massueville
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Nov 1, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast May 15, 2017
- Construction end5 months earlyforecast Mar 31, 2019
Also in Massueville