Renewal of water pipes
Federal contribution
$1.5M
$1,462,479
Federal share38%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 24, 2017
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Sainte-Julie
- Construction start
- Apr 24, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 22, 2017
- Construction end5 months earlyforecast Mar 31, 2019
Also in Sainte-Julie
- Program for the renewal of drinking water and wastewater pipes$1.2M
- Program for the renewal of drinking water and wastewater pipes$562.7K
- Program for the renewal of drinking water and wastewater pipes$483.8K
- Program for the renewal of drinking water and wastewater pipes$393.6K
- Development of a method for prioritizing single and critical segments$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49056 in the federal list. How to read these figures.