New Water Reservoir and associated site piping at the Limoges Water Treatment Plant
Federal contribution
$430,502
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of The Nation
- Construction start
- Mar 6, 2017(actual)
- Construction end
- Mar 22, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast Feb 1, 2017
- Construction end21 months lateforecast Jun 30, 2017
Also in The Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49122 in the federal list. How to read these figures.