New Water Reservoir and associated site piping at the Limoges Water Treatment Plant

The Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$430,502
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of The Nation
Construction start
Mar 6, 2017(actual)
Construction end
Mar 22, 2019(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Feb 1, 2017
  • Construction end21 months lateforecast Jun 30, 2017