Back to projects

Turtle Pond Stormwater Management Pond Sediment Removal and Clean Out

Brantford, Ontario

completeWastewaterCWWF
Federal contribution
$267,257
Federal share50%

of $534.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 19, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Brantford
Construction start
Sep 1, 2017(actual)
Construction end
Oct 29, 2019(actual)

Also in Brantford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49124 in the federal list. How to read these figures.