Back to projects

Stormwater Collection Network Assessment and Study

Brantford, Ontario

completeWastewaterCWWF
Federal contribution
$34,754
Federal share26%

of $132.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Brantford
Construction start
Nov 30, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start9 months lateforecast Mar 15, 2017

Also in Brantford