Upgrading of existing 300mm Sanitary Sewer on Greenwich Drive to 450mm

Brantford, Ontario

completeWastewaterCWWF
Federal contribution
$1.8M
$1,797,788
Federal share50%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Brantford
Construction start
Jun 18, 2016(actual)
Construction end
Apr 19, 2018(actual)

Against the original forecast

  • Construction start9 months earlyforecast Mar 15, 2017
  • Construction end6 weeks earlyforecast Jun 1, 2018

Also in Brantford