Wastewater Treatment Plant Electrical Transformer Replacement
Federal contribution
$1.5M
$1,471,749
Federal share40%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Brantford
- Construction start
- Jun 5, 2017(actual)
- Construction end
- Aug 1, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 15, 2017
- Construction end4 months lateforecast Mar 31, 2019
Also in Brantford
- Laurier Brantford YMCA Athletics and Recreation Complex$16.7M
- Construction of Wayne Gretsky Centre Four-Pad Arena$13.0M
- Upgrade of the Water Treatment Plant$5.4M
- Enclosing Open Concept Classrooms; HVAC; Water filling Station; Hallway door hold open devices; Entrance door security access$4.7M
- Grand Riverview$4.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49127 in the federal list. How to read these figures.