Shellard Lane Storm Water Management Pond Capital Rehabilitation

Brantford, Ontario

completeWastewaterCWWF
Federal contribution
$193,594
Federal share50%

of $388.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Brantford
Construction start
Dec 1, 2017(actual)
Construction end
Oct 29, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Jun 1, 2017