Bring up to code and maintain assets – Water treatment plant

Bécancour, Quebec

completeDrinking WaterCWWF
Federal contribution
$979,098
Federal share50%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
2018
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Bécancour
Construction start
Oct 20, 2017(actual)
Construction end
Nov 12, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 14, 2017
  • Construction end5 weeks earlyforecast Dec 20, 2018