Peace River Bridge

Peace River, Alberta

completeHighways and RoadsNRP
Federal contribution
$74.4M
$74,395,500
Federal share50%

of $149.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2017
20182019202020212022
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Oct 17, 2017(actual)
Construction end
Nov 9, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 1, 2017

Also in Peace River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49167 in the federal list. How to read these figures.