Peace River Landslide Stabilization

Peace River, Alberta

completeDisaster MitigationNRP
Federal contribution
$1.7M
$1,698,119
Federal share33%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2018
201820192020202120222023
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Town of Peace River
Construction start
Dec 20, 2017(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2022