Replacement of wastewater pipes

Saint-Joseph-de-Beauce, Quebec

completeWastewaterSCF
Federal contribution
$425,049
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 30, 2018(actual)
Construction end
Mar 18, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2018
  • Construction end6 months earlyforecast Sep 30, 2020

Also in Saint-Joseph-de-Beauce

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49207 in the federal list. How to read these figures.