Back to projects

Drinking water upgrade / Saint-Joseph

Saint-Joseph-de-Beauce, Quebec

completeDrinking WaterCWWF
Federal contribution
$3.4M
$3,426,840
Federal share50%

of $6.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20172018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 17, 2017(actual)
Construction end
Aug 7, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 5, 2017
  • Construction end8 months earlyforecast Mar 31, 2019

Also in Saint-Joseph-de-Beauce

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48253 in the federal list. How to read these figures.