Back to projects

Pipestone - Handi-Van Purchase

Pipestone, Manitoba

completePublic TransitPTIF
Federal contribution
$50,225
Federal share50%

of $100.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 29, 2017
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 19, 2017(actual)
Construction end
Dec 5, 2017(actual)