Lagoon Expansion - Pipestone
Federal contribution
$1.7M
$1,685,725
Federal share34%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of Pipestone
- Construction start
- Nov 7, 2016(actual)
- Construction end
- Oct 23, 2018(actual)
Against the original forecast
- Construction start6 months earlyforecast May 1, 2017
Also in Pipestone
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47117 in the federal list. How to read these figures.