West Interlake - Lakeshore Handivan Parking Facility
Federal contribution
$25,058
Federal share49%
of $51.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Municipality of West Interlake
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Jan 12, 2018(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 10, 2017
- Construction end3 months earlyforecast Mar 31, 2018
Also in West Interlake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49278 in the federal list. How to read these figures.