Purchase of a vehicle and supporting infrastructure to enhance transit services and medical shuttle between the rural Municipalities of West Interlake & Grahamdale including rural Municipality of Col
Federal contribution
$229,677
Federal share80%
of $287.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 27, 2024
202320242025
Built
Approved 17 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Lakeshore Handivan Association, Inc.
- Construction start
- Mar 15, 2023(actual)
- Construction end
- Sep 30, 2025(actual)