Bulk Water Upgrades

Mossey River, Manitoba

completeDrinking WaterCWWF
Federal contribution
$6,149
Federal share41%

of $15.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 31, 2018(actual)
Construction end
Jun 4, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 16, 2017
  • Construction end7 months lateforecast Oct 31, 2017

Also in Mossey River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49297 in the federal list. How to read these figures.