Lagoon Upgrade

Stonewall, Manitoba

completeWastewaterCWWF
Federal contribution
$2.3M
$2,300,000
Federal share50%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Stonewall
Construction start
Sep 12, 2017(actual)
Construction end
Nov 19, 2018(actual)

Against the original forecast

  • Construction end9 months earlyforecast Aug 30, 2019