Back to projects

Sewage Force Main Upgrade

Woodlands, Manitoba

completeWastewaterCWWF
Federal contribution
$137,290
Federal share35%

of $389.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 28, 2017(actual)
Construction end
Jan 19, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Nov 3, 2017
  • Construction end7 weeks lateforecast Nov 30, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49309 in the federal list. How to read these figures.