Union School Road Culvert Rehabilitation

Neebing, Ontario

completeWastewaterCWWF
Federal contribution
$8,560
Federal share50%

of $17.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedFeb 28, 2018
2018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Neebing
Construction start
Aug 28, 2017(actual)
Construction end
Sep 30, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2017
  • Construction end4 weeks earlyforecast Oct 31, 2017