Back to projects

Replace (2) 2006 Eldorado (Unit #700& #702) with new 30' Conventional Low Floor Accessible Buses to enhance service reliability and ridership demands

Collingwood, Ontario

completePublic TransitPTIF
Federal contribution
$413,601
Federal share49%

of $846.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 12, 2017
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Collingwood
Construction start
May 8, 2017(actual)
Construction end
Jul 13, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 15, 2017
  • Construction end8 months earlyforecast Mar 15, 2018

Also in Collingwood

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49364 in the federal list. How to read these figures.