Back to projects

Construction of a new Transit Maintenance Garage & Public Works Yard

Peterborough, Ontario

completePublic TransitPTIF
Federal contribution
$1.9M
$1,900,000
Federal share33%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedFeb 26, 2018
20182019
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Peterborough
Construction start
Aug 14, 2017(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Dec 31, 2018