Back to projects

Purchase one new accessible bus for service expansion

Kapuskasing, Ontario

completePublic TransitPTIF
Federal contribution
$57,167
Federal share50%

of $114.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 14, 2017
ApprovedMar 19, 2018
201720182019
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Kapuskasing
Construction start
Jan 1, 2017(actual)
Construction end
Mar 31, 2019(actual)