Purchase of 1 Accessible Transit Vehicle

Meaford, Ontario

completePublic TransitPTIF
Federal contribution
$35,616
Federal share50%

of $71.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2017
2018
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
Municipality of Meaford
Construction start
Oct 12, 2017(actual)
Construction end
Dec 21, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 3, 2017
  • Construction end3 months earlyforecast Mar 31, 2018