Back to projects

Purchase of computer aided dispatch / automated vehicle location (CAD/AVL) equipment for the 3 existing Inter-municipal Transit buses

Niagara, Ontario

completePublic TransitPTIF
Federal contribution
$46,851
Federal share39%

of $120.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Oct 10, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start8 months lateforecast Jan 30, 2017

Also in Niagara

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49494 in the federal list. How to read these figures.