Installation of security cameras on all transit fleet vehicles
Federal contribution
$88,000
Federal share50%
of $176.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 14, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 4 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of North Bay
- Construction start
- Sep 4, 2018(actual)
- Construction end
- Jan 15, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2018
- Construction end2 weeks lateforecast Dec 31, 2018