Installation of security cameras on all transit fleet vehicles

North Bay, Ontario

completePublic TransitPTIF
Federal contribution
$88,000
Federal share50%

of $176.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 14, 2017
ApprovedJul 10, 2017
20182019
Built

Approved 4 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of North Bay
Construction start
Sep 4, 2018(actual)
Construction end
Jan 15, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2018
  • Construction end2 weeks lateforecast Dec 31, 2018