Various improvements to the Transit Vehicle Storage Facility

North Bay, Ontario

completePublic TransitPTIF
Federal contribution
$263,078
Federal share46%

of $578.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 14, 2017
ApprovedMar 27, 2018
2018
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of North Bay
Construction start
Dec 12, 2017(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast May 1, 2017
  • Construction end8 months earlyforecast Mar 31, 2019

Also in North Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49501 in the federal list. How to read these figures.