Various improvements to the Transit Vehicle Wash Facility
Federal contribution
$45,198
Federal share45%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 14, 2017
ApprovedJul 10, 2017
201820192020
Built
Approved 4 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of North Bay
- Construction start
- Oct 3, 2017(actual)
- Construction end
- Feb 3, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2017
- Construction end10 months lateforecast Mar 31, 2019
Also in North Bay