Enhancing the accessibility of all bus stops
Federal contribution
$48,390
Federal share48%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 14, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 4 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of North Bay
- Construction start
- Jul 12, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
Also in North Bay