Introduction of passenger counters on all transit fleet vehicles
Federal contribution
$59,894
Federal share40%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 14, 2017
ApprovedJul 10, 2017
2018
Built
Approved 4 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of North Bay
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end2 months earlyforecast Jan 31, 2019
Also in North Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49507 in the federal list. How to read these figures.