Replace one accessible Caremobile Van

Peterborough, Ontario

completePublic TransitPTIF
Federal contribution
$38,046
Federal share38%

of $100.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
County of Peterborough
Construction start
Aug 28, 2017(actual)
Construction end
Mar 15, 2018(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 8, 2017
  • Construction end6 weeks lateforecast Feb 2, 2018