Back to projects

Upgrade to Existing Water Treatment Plant Raw Water Low Lift Pumps

Emo, Ontario

completeDrinking WaterCWWF
Federal contribution
$20,739
Federal share46%

of $45.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Emo
Construction start
Jul 1, 2018(actual)
Construction end
Nov 25, 2019(actual)

Against the original forecast

  • Construction start15 months lateforecast Apr 1, 2017
  • Construction end4 months lateforecast Jul 31, 2019

Also in Emo