Water/Sewer Replacement 2017
Summerside, Prince Edward Island
Federal contribution
$1.6M
$1,551,288
Federal share50%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Summerside
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Sep 28, 2018(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Nov 9, 2018
Also in Summerside
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49550 in the federal list. How to read these figures.