Storm sewer installation and remediation in the Thorold South catchment area

Thorold, Ontario

completeWastewaterCWWF
Federal contribution
$127,998
Federal share50%

of $256.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Thorold
Construction start
Aug 28, 2017(actual)
Construction end
Jan 31, 2020(actual)

Against the original forecast

  • Construction start6 months lateforecast Feb 15, 2017
  • Construction end4 weeks earlyforecast Mar 1, 2020