Storm sewer installation and remediation in the Thorold South catchment area
Federal contribution
$127,998
Federal share50%
of $256.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Thorold
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Jan 31, 2020(actual)
Against the original forecast
- Construction start6 months lateforecast Feb 15, 2017
- Construction end4 weeks earlyforecast Mar 1, 2020
Also in Thorold
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49556 in the federal list. How to read these figures.