Water Street Culvert Replacement and Creek Enhancement

Summerside, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$633,824
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Summerside
Construction start
Sep 11, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction end11 months lateforecast Dec 31, 2017