Lift Station SCADA
Summerside, Prince Edward Island
Federal contribution
$176,720
Federal share50%
of $353.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2017
20182019
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Summerside
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Oct 1, 2017
- Construction end18 months lateforecast Mar 31, 2018
Also in Summerside