Back to projects

Upgrade heating control systems for buildings

Québec, Quebec

completePublic TransitPTIF
Federal contribution
$77,510
Federal share50%

of $155.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 16, 2018
201820192020
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Mar 1, 2018(actual)
Construction end
Mar 31, 2020(actual)

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49612 in the federal list. How to read these figures.