Back to projects

Upgrade of lighting for the garage at the Lebourgneuf operational centre

Québec, Quebec

completePublic TransitPTIF
Federal contribution
$351,686
Federal share50%

of $703.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 18, 2017
2017201820192020
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Also in Québec