Upgrade of lighting for the garage at the Lebourgneuf operational centre
Federal contribution
$351,686
Federal share50%
of $703.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2017
2017201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- Jan 1, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Québec