Surface Way Building Replacement
Federal contribution
$15.2M
$15,203,831
Federal share50%
of $30.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 13, 2017
ApprovedMar 27, 2018
2017201820192020
Built
Approved 5 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Dec 1, 2016(actual)
- Construction end
- Jan 16, 2020(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 1, 2016
- Construction end18 months earlyforecast Jul 31, 2021
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49698 in the federal list. How to read these figures.