Back to projects

Surface Way Building Replacement

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$15.2M
$15,203,831
Federal share50%

of $30.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 13, 2017
ApprovedMar 27, 2018
2017201820192020
Built

Approved 5 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Dec 1, 2016(actual)
Construction end
Jan 16, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2016
  • Construction end18 months earlyforecast Jul 31, 2021

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49698 in the federal list. How to read these figures.