King Street Modelling Study

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$284,124
Federal share47%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2017
2017201820192020
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Dec 1, 2016(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 1, 2016
  • Construction end3 months lateforecast Dec 31, 2019