Reimagining Yonge Street Design
Federal contribution
$455,615
Federal share9%
of $5.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 13, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 5 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 15, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2016
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49700 in the federal list. How to read these figures.